| Assessment Year | 2023 |
|---|---|
| Principal Product | Office Space |
| NAICS | 551114: Corporate, Subsidiary, and Regional Managing Offices |
| SIC | 6541: Title Abstract Offices |
| Sales Range | less than $500 k |
| # of Employees | 187 |
| Plant Area |
79,838
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 2,625
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $78,299 | 849,398 |
kWh
|
$0.092 |
| Electricity Demand | $28,377 | 2,211 |
kW-mo/yr
|
$12.83 |
| Electricity Fees | $11,761 | - |
|
- |
| Natural Gas | $12,543 | 1,513 |
MMBtu
|
$8.29 |
| TOTAL YEARLY COSTS | $130,980 | |||
| RECOMMENDED SAVINGS* | $104,880 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $36,464 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $27,395 | $19,066 |
$16,757
182,145
kWh
|
$10,637
-
kW-mo/yr
|
- | |
| 02 | 2.7135: Install occupancy sensors | $9,069 | $7,303 |
$8,291
90,125
kWh
|
$778
-
kW-mo/yr
|
- | |
| 03 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $3,672 | - |
$2,148
23,872
kWh
|
- |
$1,524
-
MMBtu
|
|
| 04 | 2.9114: Use solar heat to make electricty | $43,347 | $366,628 |
$36,419
395,854
kWh
|
$6,928
-
kW-mo/yr
|
- | |
| 05 | 2.7234: Use heat pump for space conditioning | $21,396 | $151,345 |
$23,966
260,495
kWh
|
$(-2,569.6)
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $104,880 | $544,342 |
$87,582
952,491
kWh
|
$15,774
-
kW-mo/yr
|
$1,524
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $36,464 | $26,369 |
$25,049
272,270
kWh
|
$11,415
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs