ITAC Assessment: IC0262
ITAC logo
ITAC Assessment: IC0262
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Farm Machinery and Equipment
NAICS 333111: Farm Machinery and Equipment Manufacturing
SIC 3523: Farm Machinery and Equipment
Sales Range $100
M
to 500
M
# of Employees 145
Plant Area 273,500
ft2
Annual Production 6,700
ton
Production Hrs. Annual 4,225
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $126,811 2,605,907
kWh
Electricity Demand $89,044 15,635
kW-mo/yr
Natural Gas $23,533 31,507
MMBtu
TOTAL YEARLY COSTS $239,388
RECOMMENDED SAVINGS* $9,034 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,327 $4,150 $5,508
112,400
kWh
$1,819
-
kW-mo/yr
02 2.7311: Ventilation system to shut off when room is not in use $356 $5,338 $356
7,274
kWh
-
03 2.4322: Use or replace with energy efficient substitutes $1,351 $33,110 $933
19,048
kWh
$418
-
kW-mo/yr
TOTAL RECOMMENDED $9,034 $42,598 $6,797
138,722
kWh
$2,237
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs