Assessment Year | 2022 |
---|---|
Principal Product | RV Wheel Rims |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
300,000
ft2
|
Annual Production | 420,000
units
|
Production Hrs. Annual | 5,460
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $306,173 | 3,876,864 |
kWh
|
$0.079 |
Electricity Demand | $184,717 | 13,870 |
kW-mo/yr
|
$13.32 |
Electricity Fees | $(-123,759.0) | - |
|
- |
Natural Gas | $7,873 | 1,168 |
MMBtu
|
$6.74 |
TOTAL YEARLY COSTS | $375,004 | |||
RECOMMENDED SAVINGS* | $27,026 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,022 | $4,053 |
$739
9,600
kWh
|
$282
-
kW-mo/yr
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,710 | $5,524 |
$4,018
52,183
kWh
|
$1,692
-
kW-mo/yr
|
- | |
03 | 2.3212: Optimize plant power factor | $16,762 | $27,372 | - | - | $16,762 | |
04 | 2.4221: Install compressor air intakes in coolest locations | $3,533 | $230 |
$2,559
33,228
kWh
|
$974
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $27,026 | $37,179 |
$7,316
95,011
kWh
|
$2,948
-
kW-mo/yr
|
$16,762 | ||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs