*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Trailer Axle Assembly
NAICS 336350: Motor Vehicle Transmission and Power Train Parts Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $100
M
to 500
M
# of Employees 250
Plant Area 162,680
ft2
Annual Production 538,000
ton
Production Hrs. Annual 3,984
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $254,603 3,777,408
kWh
Electricity Demand $114,228 8,828
kW-mo/yr
Electricity Fees $46,153 -
Natural Gas $88,600 9,667
MMBtu
TOTAL YEARLY COSTS $503,584
RECOMMENDED SAVINGS* $212,600 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $82,031

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $49,924 $30,183 $36,182
536,817
kWh
$13,742
-
kW-mo/yr
- -
02 3.6123: Burn wood by-products for heat $42,806 $9,522 - - $42,806
-
MMBtu
-
03 2.8114: Change rate schedules or other changes in utility service $15,481 - - - - $15,481
04 2.7231: Use radiant heater for spot heating $7,794 $18,280 - - $7,794
-
MMBtu
-
05 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $77,665 $110,000 $28,318
420,159
kWh
$49,347
-
kW-mo/yr
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $16,626 $4,075 $12,000
178,042
kWh
$4,626
-
kW-mo/yr
- -
07 2.4231: Reduce the pressure of compressed air to the minimum required $2,304 $100 $1,663
24,668
kWh
$641
-
kW-mo/yr
- -
TOTAL RECOMMENDED $212,600 $172,160 $78,162
1,159,686
kWh
$68,356
-
kW-mo/yr
$50,600
-
MMBtu
$15,481
TOTAL IMPLEMENTED $82,031 $34,258 $48,182
714,859
kWh
$18,368
-
kW-mo/yr
- $15,481
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs