ITAC Assessment: IC0221
ITAC logo
ITAC Assessment: IC0221
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Manufactured Plastic Corrugated Pipe & Fittings
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 68
Plant Area 65,000
ft2
Annual Production 40,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $482,862 7,483,200
kWh
Electricity Demand $230,267 18,122
kW-mo/yr
Electricity Fees $43,066 -
Waste Disposal Costs
Water Usage $2,264 657
Tgal
Water Disposal $1,940 657
Tgal
TOTAL YEARLY COSTS $760,400
RECOMMENDED SAVINGS* $24,537 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,908

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $11,226 $7,471 $7,871
122,023
kWh
$3,355
-
kW-mo/yr
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,682 $4,200 $4,540
70,384
kWh
$142
-
kW-mo/yr
03 2.2511: Insulate bare equipment $8,629 $5,550 $8,629
133,786
kWh
-
TOTAL RECOMMENDED $24,537 $17,221 $21,039
326,193
kWh
$3,498
-
kW-mo/yr
TOTAL IMPLEMENTED $15,908 $11,671 $12,410
192,407
kWh
$3,498
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs