ITAC Assessment: IC0216
ITAC logo
ITAC Assessment: IC0216
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Wastewater Treatment Plant
NAICS 221310: Water Supply and Irrigation Systems
SIC 4941: Water Supply
Sales Range less than $500
k
# of Employees 51
Plant Area 1,218,863
ft2
Annual Production 1,218
units
Production Hrs. Annual 8,760
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $181,492 4,646,002
kWh
Electricity Demand $217,034 8,444
kW-mo/yr
Electricity Fees $21,021 -
Natural Gas $35,952 6,329
MMBtu
TOTAL YEARLY COSTS $455,500
RECOMMENDED SAVINGS* $15,123 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,288

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.3212: Optimize plant power factor $8,388 $10,700 - - $8,388
02 2.6231: Utilize controls to operate equipment only when needed $1,893 $2,460 $1,893
48,417
kWh
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,900 $3,585 $2,545
65,904
kWh
$355
-
kW-mo/yr
-
04 2.9114: Use solar heat to make electricty $1,942 $15,000 $436
14,523
kWh
$1,506
-
kW-mo/yr
-
TOTAL RECOMMENDED $15,123 $31,745 $4,874
128,844
kWh
$1,861
-
kW-mo/yr
$8,388
TOTAL IMPLEMENTED $11,288 $14,285 $2,545
65,904
kWh
$355
-
kW-mo/yr
$8,388
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs