Assessment Year | 2019 |
---|---|
Principal Product | Wastewater Treatment Plant |
NAICS | 221310: Water Supply and Irrigation Systems |
SIC | 4941: Water Supply |
Sales Range | less than $500 k |
# of Employees | 51 |
Plant Area |
1,218,863
ft2
|
Annual Production | 1,218
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $181,492 | 4,646,002 |
kWh
|
$0.039 |
Electricity Demand | $217,034 | 8,444 |
kW-mo/yr
|
$25.70 |
Electricity Fees | $21,021 | - |
|
- |
Natural Gas | $35,952 | 6,329 |
MMBtu
|
$5.68 |
TOTAL YEARLY COSTS | $455,500 | |||
RECOMMENDED SAVINGS* | $15,123 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,288 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $8,388 | $10,700 | - | - | $8,388 | |
02 | 2.6231: Utilize controls to operate equipment only when needed | $1,893 | $2,460 |
$1,893
48,417
kWh
|
- | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,900 | $3,585 |
$2,545
65,904
kWh
|
$355
-
kW-mo/yr
|
- | |
04 | 2.9114: Use solar heat to make electricty | $1,942 | $15,000 |
$436
14,523
kWh
|
$1,506
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $15,123 | $31,745 |
$4,874
128,844
kWh
|
$1,861
-
kW-mo/yr
|
$8,388 | ||
TOTAL IMPLEMENTED | $11,288 | $14,285 |
$2,545
65,904
kWh
|
$355
-
kW-mo/yr
|
$8,388 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs