Assessment Year | 2011 |
---|---|
Principal Product | Containers |
NAICS | 321920: Wood Container and Pallet Manufacturing |
SIC | 2448: Wood Pallets and Skids |
Sales Range | $1 M to 5M |
# of Employees | 249 |
Plant Area |
60,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $120,383 | 1,860,702 |
kWh
|
$0.065 |
Electricity Demand | $58,195 | 6,284 |
kW-mo/yr
|
$9.26 |
Natural Gas | $83,592 | 15,920 |
MMBtu
|
$5.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $65,797 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,132 | $2,264 |
$823
12,726
kWh
|
$309
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $32,171 | $190,302 |
$23,245
352,262
kWh
|
$8,926
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $25,672 | $128,355 |
$18,666
288,494
kWh
|
$7,006
-
kW-mo/yr
|
- | |
04 | 2.7135: Install occupancy sensors | $408 | $3,264 |
$408
6,301
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $407 | - |
$407
6,269
kWh
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,650 | $2,650 |
$2,650
40,964
kWh
|
- | - | |
07 | 2.1133: Adjust burners for efficient operation | $3,224 | $1,612 | - | - |
$3,224
-
MMBtu
|
|
08 | 2.4322: Use or replace with energy efficient substitutes | $133 | - |
$111
1,700
kWh
|
$22
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $65,797 | $328,447 |
$46,310
708,716
kWh
|
$16,263
-
kW-mo/yr
|
$3,224
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs