Assessment Year | 1999 |
---|---|
Principal Product | Fabricated Rubber Products |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 45 |
Plant Area |
32,000
ft2
|
Annual Production | 700,000
lb
|
Production Hrs. Annual | 4,290
hrs
|
Location (State) | not found |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $40,641 | 646,249 |
kWh
|
$0.063 |
Electricity Demand | $8,133 | 3,456 |
kW-mo/yr
|
$2.35 |
Electricity Fees | $4,466 | - |
|
- |
Natural Gas | $4,685 | 1,142 |
MMBtu
|
$4.10 |
Other Gas | $1,513 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,543 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $29,305 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $1,333 | $2,050 |
$1,227
19,050
kWh
|
$106
-
kW-mo/yr
|
- | - | - | |
02 | 2.7135: Install occupancy sensors | $325 | $675 |
$290
4,396
kWh
|
$35
-
kW-mo/yr
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $141 | - |
$128
2,052
kWh
|
$13
-
kW-mo/yr
|
- | - | - | |
04 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $25,426 | $5,000 | - | - | - |
$25,426
-
gal
|
- | |
05 | 3.4114: Replace city water with recycled water via cooling tower | $1,238 | $3,500 | - | - |
$1,238
-
Tgal
|
- | - | |
06 | 4.513: Re-arrange equipment layout to reduce labor costs | $2,080 | $6,500 | - | - | - | - | $2,080 | |
TOTAL RECOMMENDED | $30,543 | $17,725 |
$1,645
25,498
kWh
|
$154
-
kW-mo/yr
|
$1,238
-
Tgal
|
$25,426
-
gal
|
$2,080 | ||
TOTAL IMPLEMENTED | $29,305 | $14,225 |
$1,645
25,498
kWh
|
$154
-
kW-mo/yr
|
- |
$25,426
-
gal
|
$2,080 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs