Assessment Year | 2011 |
---|---|
Principal Product | pharmaceutical excipient |
NAICS | 325613: Surface Active Agent Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $10 M to 50M |
# of Employees | 33 |
Plant Area |
57,000
ft2
|
Annual Production | 20,000
ton
|
Production Hrs. Annual | 8,496
hrs
|
Location (State) | Wisconsin |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $117,547 | 1,728,140 |
kWh
|
$0.068 |
Electricity Demand | $42,485 | 3,785 |
kW-mo/yr
|
$11.22 |
Electricity Fees | $2,554 | - |
|
- |
Natural Gas | $337,622 | 58,181 |
MMBtu
|
$5.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $330,199 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $1,075 | $200 | - | - |
$1,057
-
MMBtu
|
- | - | - |
$18
-
Tgal
|
|
02 | 4.132: Purchase new equipment to reduce material use / cost | $66,621 | $315,096 |
$(-29,389.0)
(-432,180)
kWh
|
$(-13,722.0)
-
kW-mo/yr
|
- | - |
$114,043
-
gal
|
$(-4,311.0) | - | |
03 | 2.7135: Install occupancy sensors | $604 | $1,719 |
$435
6,414
kWh
|
$169
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.6211: Conserve energy by efficient use of vending machines | $283 | $1 |
$231
3,400
kWh
|
$52
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $1,057 | $115 | - | - |
$1,057
-
MMBtu
|
- | - | - | - | |
06 | 2.2136: Install / repair insulation on steam lines | $205 | $334 | - | - |
$205
-
MMBtu
|
- | - | - | - | |
07 | 2.2612: Use cooling tower water instead of refrigeration | $260,354 | $102,100 |
$5,021
73,848
kWh
|
$1,172
-
kW-mo/yr
|
- |
$254,161
-
Tgal
|
- | - | - | |
TOTAL RECOMMENDED | $330,199 | $419,565 |
$(-23,702.0)
(-348,518)
kWh
|
$(-12,329.0)
-
kW-mo/yr
|
$2,319
-
MMBtu
|
$254,161
-
Tgal
|
$114,043
-
gal
|
$(-4,311.0) |
$18
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs