| Assessment Year | 2010 |
|---|---|
| Principal Product | Plastic Injection Molds and Plastic Parts |
| NAICS | 333511: Industrial Mold Manufacturing |
| SIC | 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
28,000
ft2
|
| Annual Production | 100,000
pieces
|
| Production Hrs. Annual | 6,024
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $78,598 | 1,233,872 |
kWh
|
$0.064 |
| Electricity Demand | $18,900 | 3,337 |
kW-mo/yr
|
$5.66 |
| Natural Gas | $4,264 | 611 |
MMBtu
|
$6.98 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $5,348 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,188 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $206 | $1 |
$170
2,056
kWh
|
$51
-
kW-mo/yr
|
$6 | $(-21.0) | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,982 | $15,752 |
$2,199
26,853
kWh
|
$467
-
kW-mo/yr
|
$44 | $272 | |
| 03 | 2.7135: Install occupancy sensors | $1,091 | $3,544 |
$896
10,955
kWh
|
$195
-
kW-mo/yr
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $667 | $212 |
$194
2,367
kWh
|
$19
-
kW-mo/yr
|
$346 | $108 | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $150 | $1 |
$150
1,826
kWh
|
- | - | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $252 | $1,520 |
$252
3,071
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $5,348 | $21,030 |
$3,861
47,128
kWh
|
$732
-
kW-mo/yr
|
$396 | $359 | ||
| TOTAL IMPLEMENTED | $3,188 | $15,753 |
$2,369
28,909
kWh
|
$518
-
kW-mo/yr
|
$50 | $251 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs