Assessment Year | 2006 |
---|---|
Principal Product | Liquid filled transformers |
NAICS | 334416: Capacitor, Resistor, Coil, Transformer, and Other Inductor Manufacturing |
SIC | 3612: Power, Distribution, and Specialty Transformers |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
55,000
ft2
|
Annual Production | 850
pieces
|
Production Hrs. Annual | 2,150
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $29,920 | 345,600 |
kWh
|
$0.087 |
Electricity Demand | $11,631 | 1,597 |
kW-mo/yr
|
$7.28 |
Natural Gas | $65,837 | 5,200 |
MMBtu
|
$12.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $5,740 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,740 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $2,080 | $3,690 | - |
$2,080
-
kW-mo/yr
|
- | |
02 | 2.2511: Insulate bare equipment | $1,650 | $250 | - | - |
$1,650
-
MMBtu
|
|
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,010 | $913 |
$690
7,970
kWh
|
$320
-
kW-mo/yr
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $560 | $250 |
$380
4,420
kWh
|
$180
-
kW-mo/yr
|
- | |
05 | 2.7124: Make a practice of turning off lights when not needed | $440 | - |
$440
5,100
kWh
|
- | - | |
TOTAL RECOMMENDED | $5,740 | $5,103 |
$1,510
17,490
kWh
|
$2,580
-
kW-mo/yr
|
$1,650
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,740 | $5,103 |
$1,510
17,490
kWh
|
$2,580
-
kW-mo/yr
|
$1,650
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs