ITAC Assessment: IC0165
ITAC logo
ITAC Assessment: IC0165
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Metal Containers
NAICS 332439: Other Metal Container Manufacturing
SIC 3412: Metal Shipping Barrels, Drums, Kegs, and Pails
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 59,500
ft2
Annual Production 250,000
units
Production Hrs. Annual 2,202
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $104,116 1,491,483
kWh
Electricity Demand $31,266 5,283
kW-mo/yr
Natural Gas $222,162 20,286
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $52,835 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,184

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 : $35 $81 $23
337
kWh
$12
-
kW-mo/yr
-
02 -.----: $56 $152 $50
710
kWh
$6
-
kW-mo/yr
-
03 -.----: $3,581 - - - $3,581
-
MMBtu
04 -.----: $573 $575 $573
8,214
kWh
- -
05 -.----: $197 $485 - - $197
-
MMBtu
06 -.----: $41,095 $2,038 - - $41,095
-
MMBtu
07 -.----: $6,833 $45,400 - - $6,833
-
MMBtu
08 -.----: $465 - $252
3,600
kWh
$213
-
kW-mo/yr
-
TOTAL RECOMMENDED $52,835 $48,731 $898
12,861
kWh
$231
-
kW-mo/yr
$51,706
-
MMBtu
TOTAL IMPLEMENTED $11,184 $46,460 $573
8,214
kWh
- $10,611
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs