ITAC Assessment: IC0131
ITAC logo
ITAC Assessment: IC0131
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product automotive part and supplies
NAICS 423120: Motor Vehicle Supplies and New Parts Merchant Wholesalers
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $100
M
to 500
M
# of Employees 215
Plant Area 155,000
ft2
Annual Production 6,652,000
pieces
Production Hrs. Annual 7,176
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $235,880 4,602,386
kWh
Electricity Demand $128,745 11,482
kW-mo/yr
Natural Gas $27,861 3,496
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $91,698 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $67,746

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $16,220 $65,800 $13,103
272,975
kWh
$5,112
-
kW-mo/yr
- - - - $(-1,995.0)
02 2.7142: Utilize higher efficiency lamps and/or ballasts $14,150 $105,762 $10,380
216,256
kWh
$4,058
-
kW-mo/yr
- - $1,071 - $(-1,359.0)
03 2.7135: Install occupancy sensors $1,159 $3,681 $1,042
21,700
kWh
$404
-
kW-mo/yr
- - $134 - $(-421.0)
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,771 $6,442 $1,660
34,600
kWh
$111
-
kW-mo/yr
- - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $516 $677 $145
3,005
kWh
$157
-
kW-mo/yr
- - $219 - $(-5.0)
06 2.7142: Utilize higher efficiency lamps and/or ballasts $149 $930 $42
876
kWh
$11
-
kW-mo/yr
- - $46 - $50
07 2.7124: Make a practice of turning off lights when not needed $87 - $53
1,095
kWh
$34
-
kW-mo/yr
- - - - -
08 2.4133: Use most efficient type of electric motors $1,867 $8,430 $981
20,437
kWh
$886
-
kW-mo/yr
- - - - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,474 $3,192 $1,474
30,714
kWh
- - - - - -
10 2.4231: Reduce the pressure of compressed air to the minimum required $650 - $650
13,546
kWh
- - - - - -
11 2.6211: Conserve energy by efficient use of vending machines $864 $1 $259
5,400
kWh
$605
-
kW-mo/yr
- - - - -
12 2.8114: Change rate schedules or other changes in utility service $18,231 $1 - - - - - $18,231 -
13 2.8114: Change rate schedules or other changes in utility service $1,393 $1 - - - - - $1,393 -
14 2.6242: Minimize operation of equipment maintained in standby condition $956 $7,500 - - $956
-
MMBtu
- - - -
15 3.4151: Minimize water usage $7,267 $15,000 - - - $2,267
-
gal
- $5,000 -
16 2.1233: Analyze flue gas for proper air/fuel ratio $32 $1 - - $32
-
MMBtu
- - - -
17 3.1191: Change procedures / equipment / operating conditions $5,723 $15,000 $(-482.0)
8,922
kWh
$(-191.0)
-
kW-mo/yr
- - $3,210 - $3,186
18 4.421: Modify current incentive program $19,189 $38,378 $11,048
230,119
kWh
$6,435
-
kW-mo/yr
$1,395
-
MMBtu
$311
-
gal
- - -
TOTAL RECOMMENDED $91,698 $270,796 $40,355
859,645
kWh
$17,622
-
kW-mo/yr
$2,383
-
MMBtu
$2,578
-
gal
$4,680 $24,624 $(-544.0)
TOTAL IMPLEMENTED $67,746 $256,851 $37,733
805,004
kWh
$16,872
-
kW-mo/yr
$1,427
-
MMBtu
$2,578
-
gal
$4,680 $5,000 $(-544.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs