| Assessment Year | 2007 | 
|---|---|
| Principal Product | Grey and ductile iron castings | 
| NAICS | 331511: Iron Foundries | 
| SIC | 3321: Gray and Ductile Iron Foundries | 
| Sales Range | $10 Mto 50 M | 
| # of Employees | 132 | 
| Plant Area | 63,135 
ft2
 | 
| Annual Production | 21,835,000 
lb
 | 
| Production Hrs. Annual | 6,048 
hrs
 | 
| Location (State) | Wisconsin | 
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $461,522 | 10,904,136 | 
kWh
 | $0.042 | 
| Electricity Demand | $172,379 | 68,637 | 
kW-mo/yr
 | $2.51 | 
| Natural Gas | $374,063 | 34,161 | 
MMBtu
 | $10.95 | 
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $242,523 | See individual recommendations below*Non-energy impacts included in savings. | ||
| IMPLEMENTED SAVINGS* | $72,382 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,654 | $1,710 | $15,654 372,697
                                 
kWh
 | - | - | - | - | - | - | - | |
| 02 | 2.2437: Recover waste heat from equipment | $10,523 | $6,000 | - | - | $10,523 -
                                 
MMBtu
 | - | - | - | - | - | |
| 03 | 3.4114: Replace city water with recycled water via cooling tower | $25,162 | $21,540 | $(-853.0) (-20,303)
                                 
kWh
 | $(-196.0) -
                                 
kW-mo/yr
 | - | $26,831 -
                                 
Tgal
 | - | - | $(-620.0) | - | |
| 04 | 3.5222: Use sand for other purposes (eg construction fill, cover for municipal landfills) | $103,122 | $9,600 | - | - | - | - | $103,122 -
                                 
lb
 | - | - | - | |
| 05 | 2.6222: Use drying oven (batch type) on alternate days or other optimum schedule to run equipment with full loads | $44,610 | - | - | - | $44,610 -
                                 
MMBtu
 | - | - | - | - | - | |
| 06 | 4.424: Improve space comfort conditioning | $11,886 | $10,408 | - | - | - | - | - | - | - | $11,886 | |
| 07 | 2.2314: Replace heat treating oven with more efficient unit | $21,900 | $5,883 | - | - | $21,900 -
                                 
MMBtu
 | - | - | - | - | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,566 | $11,407 | $1,022 24,320
                                 
kWh
 | $169 -
                                 
kW-mo/yr
 | - | - | - | $144 | $231 | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $249 | $260 | $70 1,664
                                 
kWh
 | $5 -
                                 
kW-mo/yr
 | - | - | - | $109 | $65 | - | |
| 10 | 2.4133: Use most efficient type of electric motors | $7,851 | $30,665 | $6,871 163,672
                                 
kWh
 | $980 -
                                 
kW-mo/yr
 | - | - | - | - | - | - | |
| TOTAL RECOMMENDED | $242,523 | $97,473 | $22,764 542,050
                                 
kWh
 | $958 -
                                 
kW-mo/yr
 | $77,033 -
                                 
MMBtu
 | $26,831 -
                                 
Tgal
 | $103,122 -
                                 
lb
 | $253 | $(-324.0) | $11,886 | ||
| TOTAL IMPLEMENTED | $72,382 | $71,465 | $22,764 542,050
                                 
kWh
 | $958 -
                                 
kW-mo/yr
 | $21,900 -
                                 
MMBtu
 | $26,831 -
                                 
Tgal
 | - | $253 | $(-324.0) | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs
             
             
            