ITAC Assessment: IC0120
ITAC logo
ITAC Assessment: IC0120
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product spring wire
NAICS 331222: Steel Wire Drawing
SIC 3315: Steel Wiredrawing and Steel Nails and Spikes
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 200,000
ft2
Annual Production 52,000,000
lb
Production Hrs. Annual 8,424
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $569,060 9,392,768
kWh
Electricity Demand $75,482 5,874
kW-mo/yr
Electricity Fees $5,212 -
Natural Gas $1,019,343 121,761
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $371,800 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $340,488

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 3.5145: Recover and reuse spent acid baths $132,386 $176,160 $(-85.0)
(-1,400)
kWh
- $132,526
-
gal
- $(-55.0) -
02 2.1233: Analyze flue gas for proper air/fuel ratio $916 - - $916
-
MMBtu
- - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,452 $8,047 $3,408
55,862
kWh
- - $188 $856 -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,943 $1,300 $3,943
64,694
kWh
- - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $447 $911 $250
4,100
kWh
- - $56 $141 -
06 2.7135: Install occupancy sensors $586 $639 $586
9,609
kWh
- - - - -
07 2.4133: Use most efficient type of electric motors $12,533 $18,187 $12,533
205,420
kWh
- - - - -
08 2.2121: Increase amount of condensate returned $29,735 $76,800 - $18,422
-
MMBtu
- - - $11,313
-
Tgal
09 2.2414: Use waste heat from hot flue gases to preheat $114,144 $385,200 $(-4,964.0)
(-81,369)
kWh
$119,108
-
MMBtu
- - - -
10 2.4323: Use optimum size and capacity equipment $991 $7,638 $991
16,243
kWh
- - - - -
11 2.1113: Reduce combustion air flow to optimum $71,667 $6,720 - $71,667
-
MMBtu
- - - -
TOTAL RECOMMENDED $371,800 $681,602 $16,662
273,159
kWh
$210,113
-
MMBtu
$132,526
-
gal
$244 $942 $11,313
-
Tgal
TOTAL IMPLEMENTED $340,488 $596,525 $15,085
247,307
kWh
$191,691
-
MMBtu
$132,526
-
gal
$244 $942 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs