| Assessment Year | 2006 |
|---|---|
| Principal Product | door modules |
| NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
| SIC | 3429: Hardware, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 142 |
| Plant Area |
65,000
ft2
|
| Annual Production | 1,077,600
pieces
|
| Production Hrs. Annual | 4,144
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $46,048 | 981,021 |
kWh
|
$0.047 |
| Electricity Demand | $29,287 | 2,393 |
kW-mo/yr
|
$12.24 |
| Electricity Fees | $240 | - |
|
- |
| Natural Gas | $96,202 | 8,063 |
MMBtu
|
$11.93 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $26,784 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $26,165 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $3,603 | $6,000 | - | - |
$3,603
-
MMBtu
|
- | - | |
| 02 | 2.2437: Recover waste heat from equipment | $3,321 | $1,100 |
$2,468
52,560
kWh
|
$853
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $294 | - |
$221
4,703
kWh
|
$73
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7261: Install timers and/or thermostats | $15,127 | $218 | - | - |
$15,127
-
MMBtu
|
- | - | |
| 05 | 2.8114: Change rate schedules or other changes in utility service | $4,114 | - | - | - |
$4,114
-
MMBtu
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $325 | $274 |
$161
3,416
kWh
|
$61
-
kW-mo/yr
|
- | $53 | $50 | |
| TOTAL RECOMMENDED | $26,784 | $7,592 |
$2,850
60,679
kWh
|
$987
-
kW-mo/yr
|
$22,844
-
MMBtu
|
$53 | $50 | ||
| TOTAL IMPLEMENTED | $26,165 | $7,318 |
$2,468
52,560
kWh
|
$853
-
kW-mo/yr
|
$22,844
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs