ITAC Assessment: IC0109
ITAC logo
ITAC Assessment: IC0109
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Internal Combustion Engines
NAICS 336390: Other Motor Vehicle Parts Manufacturing
SIC 3519: Internal Combustion Engines, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 750
Plant Area 1,000,000
ft2
Annual Production 70,000
pieces
Production Hrs. Annual 6,416
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,500,000 52,223,527
kWh
Electricity Demand $446,972 100,257
kW-mo/yr
Electricity Fees $46,802 -
Natural Gas $2,000,000 413,720
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $850,326 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $62,735

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Water Consumption Savings
01 4.426: Modify workload $25,000 - - - - $25,000 -
02 2.2423: Install waste heat boiler to produce steam $437,212 $3,259,200 $126,148
1,761,687
kWh
$205,140
-
kW-mo/yr
$116,988
-
MMBtu
$(-11,064.0) -
03 2.1224: Replace boiler $294,938 $501,372 - - $294,938
-
MMBtu
- -
04 2.2414: Use waste heat from hot flue gases to preheat $17,632 $22,464 - - $17,632
-
MMBtu
- -
05 2.2135: Repair and eliminate steam leaks $1,239 $400 - - $1,138
-
MMBtu
- $101
-
Tgal
06 2.2122: Install / repair insulation on condensate lines $37,809 $131,160 - - $37,769
-
MMBtu
- $40
-
Tgal
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $36,496 $2,100 $36,496
701,853
kWh
- - - -
TOTAL RECOMMENDED $850,326 $3,916,696 $162,644
2,463,540
kWh
$205,140
-
kW-mo/yr
$468,465
-
MMBtu
$13,936 $141
-
Tgal
TOTAL IMPLEMENTED $62,735 $2,500 $36,496
701,853
kWh
- $1,138
-
MMBtu
$25,000 $101
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs