Assessment Year | 2005 |
---|---|
Principal Product | Springs |
NAICS | 332613: Spring Manufacturing |
SIC | 3495: Wire Springs |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
500,000
ft2
|
Annual Production | 0
pieces
|
Production Hrs. Annual | 8,520
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $273,684 | 7,179,200 |
kWh
|
$0.038 |
Electricity Demand | $90,776 | 15,856 |
kW-mo/yr
|
$5.73 |
Electricity Fees | $576 | - |
|
- |
Natural Gas | $855,911 | 127,232 |
MMBtu
|
$6.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $977,877 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2424: Use heat in flue gases to preheat products or materials | $9,504 | $19,598 |
$(-2,573.0)
(-77,961)
kWh
|
$(-613.0)
-
kW-mo/yr
|
$12,690
-
MMBtu
|
- | - | - | |
02 | 2.2314: Replace heat treating oven with more efficient unit | $93,103 | $4,926 | - | - |
$93,103
-
MMBtu
|
- | - | - | |
03 | 2.2414: Use waste heat from hot flue gases to preheat | $7,772 | $39,896 | - | - |
$7,772
-
MMBtu
|
- | - | - | |
04 | 2.2443: Re-use or recycle hot or cold process exhaust air | $19,487 | $61,560 |
$(-4,025.0)
(-121,967)
kWh
|
$(-957.0)
-
kW-mo/yr
|
$24,469
-
MMBtu
|
- | - | - | |
05 | 2.2314: Replace heat treating oven with more efficient unit | $13,232 | - | - | - |
$13,232
-
MMBtu
|
- | - | - | |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $22,485 | $224,000 | - | - |
$22,485
-
MMBtu
|
- | - | - | |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $799,427 | $750,000 |
$(-3,291.0)
(-99,715)
kWh
|
$(-1,931.0)
-
kW-mo/yr
|
$(-14,573.0)
-
MMBtu
|
- | - | $819,222 | |
08 | 2.6218: Turn off equipment when not in use | $358 | $262 |
$358
10,858
kWh
|
- | - | - | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,560 | $1,800 |
$3,652
110,598
kWh
|
$908
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,309 | - |
$1,017
30,835
kWh
|
$292
-
kW-mo/yr
|
- | - | - | - | |
11 | 2.4133: Use most efficient type of electric motors | $2,097 | $9,021 |
$1,604
48,640
kWh
|
$493
-
kW-mo/yr
|
- | - | - | - | |
12 | 2.4131: Size electric motors for peak operating efficiency | $3,508 | $608 |
$2,832
85,824
kWh
|
$676
-
kW-mo/yr
|
- | - | - | - | |
13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,035 | $4,016 |
$506
15,336
kWh
|
$126
-
kW-mo/yr
|
- | $88 | $315 | - | |
TOTAL RECOMMENDED | $977,877 | $1,115,687 |
$80
2,448
kWh
|
$(-1,006.0)
-
kW-mo/yr
|
$159,178
-
MMBtu
|
$88 | $315 | $819,222 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs