| Assessment Year | 2005 |
|---|---|
| Principal Product | High Quality Amorphous Boron |
| NAICS | 325180: Other Basic Inorganic Chemical Manufacturing |
| SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 8 |
| Plant Area |
22,700
ft2
|
| Annual Production | 60,000
lb
|
| Production Hrs. Annual | 3,500
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $62,250 | 716,735 |
kWh
|
$0.087 |
| Natural Gas | $55,781 | 7,077 |
MMBtu
|
$7.88 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,117 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.6231: Utilize controls to operate equipment only when needed | $12,792 | $12,792 | - |
$12,792
-
MMBtu
|
- | - | |
| 02 | 2.2136: Install / repair insulation on steam lines | $8,631 | $4,680 | - |
$8,631
-
MMBtu
|
- | - | |
| 03 | 2.2135: Repair and eliminate steam leaks | $2,344 | $1,400 | - |
$2,344
-
MMBtu
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,340 | $300 |
$1,340
15,404
kWh
|
- | - | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $240 | - |
$240
2,758
kWh
|
- | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,336 | $941 |
$269
3,097
kWh
|
- | $831 | $236 | |
| 07 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $330 | $2,800 |
$330
3,793
kWh
|
- | - | - | |
| 08 | 2.7224: Reduce space conditioning during non-working hours | $104 | $256 | - |
$104
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $27,117 | $23,169 |
$2,179
25,052
kWh
|
$23,871
-
MMBtu
|
$831 | $236 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs