| Assessment Year | 2005 |
|---|---|
| Principal Product | Steel Bridges |
| NAICS | 332313: Plate Work Manufacturing |
| SIC | 3449: Miscellaneous Structural Metal Work |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
720,000
ft2
|
| Annual Production | 20,000
ton
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $516,212 | 11,062,000 |
kWh
|
$0.047 |
| Natural Gas | $469,969 | 82,089 |
MMBtu
|
$5.73 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $107,047 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,326 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7233: Use properly designed and sized hvac equipment | $64,389 | $324,232 |
$(-17,602.0)
(-374,662)
kWh
|
$81,991
-
MMBtu
|
|
| 02 | 2.1321: Replace fossil fuel equipment with electrical equipment | $5,945 | $13,700 |
$(-29,616.0)
(-630,135)
kWh
|
$35,561
-
MMBtu
|
|
| 03 | 2.6218: Turn off equipment when not in use | $2,381 | - |
$717
15,252
kWh
|
$1,664
-
MMBtu
|
|
| 04 | 2.1134: Eliminate leaks in combustible gas lines | $14,532 | $1,400 | - |
$14,532
-
MMBtu
|
|
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,517 | - |
$1,517
32,270
kWh
|
- | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $18,283 | $6,200 |
$18,283
389,025
kWh
|
- | |
| TOTAL RECOMMENDED | $107,047 | $345,532 |
$(-26,701.0)
(-568,250)
kWh
|
$133,748
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $8,326 | $13,700 |
$(-28,899.0)
(-614,883)
kWh
|
$37,225
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs