ITAC Assessment: IC0096
ITAC logo
ITAC Assessment: IC0096
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Breading and Dry Mix Batter
NAICS 311812: Commercial Bakeries
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 126
Plant Area 113,820
ft2
Annual Production 150,000,000
lb
Production Hrs. Annual 5,856
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $213,597 4,568,062
kWh
Electricity Demand $116,346 9,581
kW-mo/yr
Electricity Fees $942 -
Natural Gas $252,288 38,242
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $110,694 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $87,279

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.1133: Adjust burners for efficient operation $37,627 $38,000 - - $37,627
-
MMBtu
- -
02 2.2427: Use waste heat from hot flue gases to preheat incoming fluids $14,724 $46,000 $(-616.0)
(-13,106)
kWh
$(-328.0)
-
kW-mo/yr
$15,668
-
MMBtu
- -
03 2.2511: Insulate bare equipment $23,508 $21,704 - - $23,508
-
MMBtu
- -
04 2.2153: Close off unneeded steam lines $2,614 $952 - - $2,614
-
MMBtu
- -
05 2.1223: Install smaller boiler (increase high fire duty cycle) $4,798 $24,000 - - $4,798
-
MMBtu
- -
06 2.2122: Install / repair insulation on condensate lines $3,478 $2,371 - - $3,478
-
MMBtu
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,476 $1,700 $4,838
102,937
kWh
$1,638
-
kW-mo/yr
- - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $146 - $146
3,107
kWh
- - - -
09 2.4231: Reduce the pressure of compressed air to the minimum required $1,250 - $837
17,804
kWh
$413
-
kW-mo/yr
- - -
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $140 $430 $92
1,950
kWh
$48
-
kW-mo/yr
- - -
11 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,209 $4,715 $796
16,942
kWh
$413
-
kW-mo/yr
- - -
12 2.4133: Use most efficient type of electric motors $10,971 $34,362 $7,166
152,493
kWh
$3,805
-
kW-mo/yr
- - -
13 2.7142: Utilize higher efficiency lamps and/or ballasts $3,009 $5,073 $1,513
32,179
kWh
$1,119
-
kW-mo/yr
- $75 $302
14 2.7142: Utilize higher efficiency lamps and/or ballasts $744 $781 $121
2,565
kWh
$48
-
kW-mo/yr
- $191 $384
TOTAL RECOMMENDED $110,694 $180,088 $14,893
316,871
kWh
$7,156
-
kW-mo/yr
$87,693
-
MMBtu
$266 $686
TOTAL IMPLEMENTED $87,279 $103,804 $13,783
293,283
kWh
$6,269
-
kW-mo/yr
$67,227
-
MMBtu
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs