Assessment Year | 2004 |
---|---|
Principal Product | Courrugate |
NAICS | 322211: Corrugated and Solid Fiber Box Manufacturing |
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 105 |
Plant Area |
200,540
ft2
|
Annual Production | 564,000
thousand feet
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $172,548 | 3,664,500 |
kWh
|
$0.047 |
Electricity Demand | $40,445 | 7,775 |
kW-mo/yr
|
$5.20 |
Electricity Fees | $38,193 | - |
|
- |
Natural Gas | $228,671 | 32,710 |
MMBtu
|
$6.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $101,891 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2124: Install de-aerator in place of condensate tank | $41,155 | $96,800 | n/a | - | - | - |
$36,565
-
MMBtu
|
$4,590
-
Tgal
|
- |
02 | 2.2136: Install / repair insulation on steam lines | $1,540 | $2,212 | n/a | - | - | - |
$1,540
-
MMBtu
|
- | - |
03 | 2.7241: Install outside air damper / economizer on hvac unit | $9,520 | $33,750 | n/a | - | - | - |
$9,520
-
MMBtu
|
- | - |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $1,992 | - | n/a | - | - | - |
$1,992
-
MMBtu
|
- | - |
05 | 2.2135: Repair and eliminate steam leaks | $7,304 | $900 | n/a | - | - | - |
$7,304
-
MMBtu
|
- | - |
06 | 2.6126: Keep solid fuels / raw materials dry | $1,999 | $11,950 | n/a | - | - | - |
$1,999
-
MMBtu
|
- | - |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,790 | $1,700 | n/a |
$1,466
27,114
kWh
|
$257
-
kW-mo/yr
|
$67 | - | - | - |
08 | 2.4322: Use or replace with energy efficient substitutes | $222 | $75 | n/a |
$213
3,947
kWh
|
- | $9 | - | - | - |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $29,026 | $142,221 | n/a |
$30,640
567,369
kWh
|
$6,045
-
kW-mo/yr
|
$1,369 | - | - | $(-9,028.0) |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $689 | $1,252 | n/a |
$146
2,698
kWh
|
$19
-
kW-mo/yr
|
$6 | - | - | $518 |
11 | 2.6126: Keep solid fuels / raw materials dry | $819 | $920 | n/a |
$784
14,516
kWh
|
- | $35 | - | - | - |
12 | 2.4133: Use most efficient type of electric motors | $1,626 | $955 | n/a |
$1,284
23,770
kWh
|
$285
-
kW-mo/yr
|
$57 | - | - | - |
13 | 2.6126: Keep solid fuels / raw materials dry | $260 | - | n/a |
$88
1,723
kWh
|
$168
-
kW-mo/yr
|
$4 | - | - | - |
14 | 2.6126: Keep solid fuels / raw materials dry | $3,949 | $750 | n/a |
$1,124
20,808
kWh
|
- | $106 |
$2,719
-
MMBtu
|
- | - |
TOTAL RECOMMENDED | $101,891 | $293,485 |
$35,745
661,945
kWh
|
$6,774
-
kW-mo/yr
|
$1,653 |
$61,639
-
MMBtu
|
$4,590
-
Tgal
|
$(-8,510.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs