ITAC Assessment: IC0038
ITAC logo
ITAC Assessment: IC0038
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Pneumatic Valves and Cylinders
NAICS
n/a
SIC 3492: Fluid Power Valves and Hose Fittings
Sales Range $5
M
to 10
M
# of Employees 55
Plant Area 31,000
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 3,443
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $33,225 594,236
kWh
Electricity Demand $23,916 2,150
kW-mo/yr
Electricity Fees $22,302 -
Natural Gas $30,284 3,168
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,169 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,057 $2,300 n/a $1,037
26,611
kWh
$1,020
-
kW-mo/yr
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,313 $13,137 n/a $841
21,558
kWh
$826
-
kW-mo/yr
- $215 - $431
03 2.7142: Utilize higher efficiency lamps and/or ballasts $487 $2,536 n/a $171
4,399
kWh
$246
-
kW-mo/yr
- $35 - $35
04 2.7491: Insulate glazing, walls, ceilings, and roofs $2,392 $27,900 n/a - - $2,392
-
MMBtu
- - -
05 4.447: Automate payroll system $19,920 $8,340 n/a - - - $4,870 $15,050 -
TOTAL RECOMMENDED $27,169 $54,213 $2,049
52,568
kWh
$2,092
-
kW-mo/yr
$2,392
-
MMBtu
$5,120 $15,050 $466
TOTAL IMPLEMENTED - - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs