Assessment Year | 2002 |
---|---|
Principal Product | Public Building and Related Furniture |
NAICS |
n/a
|
SIC | 2531: Public Building and Related Furniture |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
217,000
ft2
|
Annual Production | 400,000
pieces
|
Production Hrs. Annual | 4,845
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $83,683 | 2,286,849 |
kWh
|
$0.037 |
Electricity Demand | $66,398 | 5,388 |
kW-mo/yr
|
$12.32 |
Electricity Fees | $21,150 | - |
|
- |
Natural Gas | $123,142 | 12,210 |
MMBtu
|
$10.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $158,820 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $146,542 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,316 | $1,400 |
$1,296
33,181
kWh
|
$1,020
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,674 | $27,188 |
$2,740
70,258
kWh
|
$1,020
-
kW-mo/yr
|
$106 | - | $808 | |
03 | 2.7135: Install occupancy sensors | $2,438 | $1,225 |
$2,108
54,047
kWh
|
$330
-
kW-mo/yr
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,602 | $25,370 |
$3,868
99,167
kWh
|
$3,026
-
kW-mo/yr
|
$(-250.0) | - | $(-42.0) | |
05 | 4.426: Modify workload | $132,950 | $36,600 | - | - | $78,500 | $54,450 | - | |
06 | 4.111: Add equipment/ operators to reduce production bottleneck | $9,840 | $250 | - | - | $9,840 | - | - | |
TOTAL RECOMMENDED | $158,820 | $92,033 |
$10,012
256,653
kWh
|
$5,396
-
kW-mo/yr
|
$88,196 | $54,450 | $766 | ||
TOTAL IMPLEMENTED | $146,542 | $90,558 |
$7,904
202,606
kWh
|
$5,066
-
kW-mo/yr
|
$78,356 | $54,450 | $766 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs