ITAC Assessment: IA0568
ITAC logo
ITAC Assessment: IA0568
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Industrial and Agricultural Equipment
NAICS 333111: Farm Machinery and Equipment Manufacturing
SIC 3523: Farm Machinery and Equipment
Sales Range $100
M
to 500
M
# of Employees 340
Plant Area 166,285
ft2
Annual Production 812
units
Production Hrs. Annual 6,240
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $214,169 4,985,432
kWh
Electricity Demand $154,159 11,928
kW-mo/yr
Natural Gas $162,233 34,732
MMBtu
TOTAL YEARLY COSTS $530,561
RECOMMENDED SAVINGS* $42,206 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $38,182

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7244: Revise smoke cleanup from operations $32,058 $60,740 $5,941
138,493
kWh
$2,602
-
kW-mo/yr
$23,515
-
MMBtu
02 2.4133: Use most efficient type of electric motors $3,266 $9,189 $2,073
48,329
kWh
$1,193
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,386 $5,977 $1,314
30,624
kWh
$1,072
-
kW-mo/yr
-
04 2.2437: Recover waste heat from equipment $2,316 $5,006 - - $2,316
-
MMBtu
05 2.4221: Install compressor air intakes in coolest locations $1,708 $422 $1,142
26,588
kWh
$566
-
kW-mo/yr
-
06 2.7132: Install timers on light switches in little used areas $472 $200 $300
6,989
kWh
$172
-
kW-mo/yr
-
TOTAL RECOMMENDED $42,206 $81,534 $10,770
251,023
kWh
$5,605
-
kW-mo/yr
$25,831
-
MMBtu
TOTAL IMPLEMENTED $38,182 $76,106 $9,628
224,435
kWh
$5,039
-
kW-mo/yr
$23,515
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs