| Assessment Year | 2015 |
|---|---|
| Principal Product | OEM Metal Stampings |
| NAICS | 336370: Motor Vehicle Metal Stamping |
| SIC | 3465: Automotive Stampings |
| Sales Range | $50 M to 100M |
| # of Employees | 262 |
| Plant Area |
178,976
ft2
|
| Annual Production | 1,000,000
pieces
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $251,977 | 7,500,400 |
kWh
|
$0.034 |
| Electricity Demand | $230,847 | 14,400 |
kW-mo/yr
|
$16.03 |
| Natural Gas | $78,025 | 12,725 |
MMBtu
|
$6.13 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $64,456 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,227 | $82,355 |
$8,556
254,643
kWh
|
$9,671
-
kW-mo/yr
|
- | |
| 02 | 2.6241: Reduce temperature of process equipment when on standby | $17,173 | $8,320 |
$2,417
71,929
kWh
|
- |
$14,756
-
MMBtu
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $14,596 | $700 |
$8,150
242,568
kWh
|
$6,446
-
kW-mo/yr
|
- | |
| 04 | 2.4133: Use most efficient type of electric motors | $6,432 | $23,803 |
$3,591
106,876
kWh
|
$2,841
-
kW-mo/yr
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,809 | $140 |
$2,685
79,920
kWh
|
$2,124
-
kW-mo/yr
|
- | |
| 06 | 2.2622: Replace existing chiller with high efficiency model | $1,746 | $60 |
$904
26,905
kWh
|
$842
-
kW-mo/yr
|
- | |
| 07 | 2.7135: Install occupancy sensors | $1,065 | $2,700 |
$1,065
31,640
kWh
|
- | - | |
| 08 | 2.7134: Use photocell controls | $408 | $2,000 |
$218
6,501
kWh
|
$190
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $64,456 | $120,078 |
$27,586
820,982
kWh
|
$22,114
-
kW-mo/yr
|
$14,756
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs