Assessment Year | 2015 |
---|---|
Principal Product | Service Vehicles |
NAICS | 336211: Motor Vehicle Body Manufacturing |
SIC | 3713: Truck and Bus Bodies |
Sales Range | $100 M to 500M |
# of Employees | 400 |
Plant Area |
325,000
ft2
|
Annual Production | 3,300
pieces
|
Production Hrs. Annual | 5,100
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $272,108 | 4,972,529 |
kWh
|
$0.055 |
Electricity Demand | $173,035 | 9,622 |
kW-mo/yr
|
$17.98 |
Electricity Fees | $13,661 | - |
|
- |
Natural Gas | $157,345 | 39,277 |
MMBtu
|
$4.01 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $28,101 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,210 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,857 | $19,775 |
$2,709
49,440
kWh
|
$3,770
-
kW-mo/yr
|
$3,378
-
MMBtu
|
|
02 | 2.4133: Use most efficient type of electric motors | $6,005 | $1,049 |
$3,361
61,329
kWh
|
$2,644
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,225 | $7,848 |
$1,684
30,681
kWh
|
$541
-
kW-mo/yr
|
- | |
04 | 2.7124: Make a practice of turning off lights when not needed | $2,136 | $210 |
$2,136
38,984
kWh
|
- | - | |
05 | 2.2437: Recover waste heat from equipment | $2,294 | $2,575 | - | - |
$2,294
-
MMBtu
|
|
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,994 | $4,066 |
$2,236
40,800
kWh
|
$1,758
-
kW-mo/yr
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $993 | $1,342 |
$553
10,098
kWh
|
$440
-
kW-mo/yr
|
- | |
08 | 2.7135: Install occupancy sensors | $597 | $2,226 |
$597
10,891
kWh
|
- | - | |
TOTAL RECOMMENDED | $28,101 | $39,091 |
$13,276
242,223
kWh
|
$9,153
-
kW-mo/yr
|
$5,672
-
MMBtu
|
||
TOTAL IMPLEMENTED | $25,210 | $34,290 |
$12,679
231,332
kWh
|
$9,153
-
kW-mo/yr
|
$3,378
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs