| Assessment Year | 2014 |
|---|---|
| Principal Product | Machined Aluminum Parts |
| NAICS | 332439: Other Metal Container Manufacturing |
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 220 |
| Plant Area |
75,000
ft2
|
| Annual Production | 1,300,000
pieces
|
| Production Hrs. Annual | 6,149
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $164,807 | 2,616,000 |
kWh
|
$0.063 |
| Electricity Demand | $61,654 | 5,818 |
kW-mo/yr
|
$10.60 |
| Electricity Fees | $4,032 | - |
|
- |
| Natural Gas | $34,344 | 4,899 |
MMBtu
|
$7.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $39,152 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,219 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,330 | $730 |
$6,282
99,733
kWh
|
$2,048
-
kW-mo/yr
|
- | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $24,087 | $20,750 |
$1,916
30,407
kWh
|
$22,171
-
kW-mo/yr
|
- | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $1,354 | $105 |
$1,100
17,428
kWh
|
$254
-
kW-mo/yr
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $846 | $1,491 |
$846
13,424
kWh
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $584 | $687 |
$318
5,773
kWh
|
$266
-
kW-mo/yr
|
- | |
| 06 | 2.2511: Insulate bare equipment | $3,951 | $100 |
$1,661
26,379
kWh
|
$545
-
kW-mo/yr
|
$1,745
-
MMBtu
|
|
| TOTAL RECOMMENDED | $39,152 | $23,863 |
$12,123
193,144
kWh
|
$25,284
-
kW-mo/yr
|
$1,745
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $14,219 | $1,622 |
$9,361
149,313
kWh
|
$3,113
-
kW-mo/yr
|
$1,745
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs