ITAC Assessment: IA0498
ITAC logo
ITAC Assessment: IA0498
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Illuminated Signs
NAICS 339950: Sign Manufacturing
SIC 3399: Primary Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 105
Plant Area 77,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,210
hrs
Location (State) South Dakota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $25,163 644,950
kWh
Electricity Demand $43,427 3,949
kW-mo/yr
Natural Gas $26,288 3,947
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $15,979 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,654

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7141: Lower light fixtures in high ceiling areas $2,917 $9,898 $1,691
28,509
kWh
$1,226
-
kW-mo/yr
-
02 2.7135: Install occupancy sensors $901 $525 $901
18,660
kWh
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $753 $660 $248
7,716
kWh
$505
-
kW-mo/yr
-
04 2.3212: Optimize plant power factor $5,092 $3,443 - - $5,092
05 2.3212: Optimize plant power factor $6,316 $3,693 - - $6,316
TOTAL RECOMMENDED $15,979 $18,219 $2,840
54,885
kWh
$1,731
-
kW-mo/yr
$11,408
TOTAL IMPLEMENTED $1,654 $1,185 $1,149
26,376
kWh
$505
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs