| Assessment Year | 2012 |
|---|---|
| Principal Product | Park Equipment |
| NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
| SIC | 3291: Abrasive Products |
| Sales Range | $10 M to 50M |
| # of Employees | 63 |
| Plant Area |
154,500
ft2
|
| Annual Production | 7,000,000
lb
|
| Production Hrs. Annual | 2,470
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $43,701 | 918,680 |
kWh
|
$0.048 |
| Electricity Demand | $37,442 | 6,242 |
kW-mo/yr
|
$6.00 |
| Natural Gas | $30,183 | 3,835 |
MMBtu
|
$7.87 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,739 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $10,329 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,624 | $4,936 |
$977
20,682
kWh
|
$647
-
kW-mo/yr
|
|
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,696 | $69,009 |
$6,016
127,452
kWh
|
$3,680
-
kW-mo/yr
|
|
| 03 | 2.7135: Install occupancy sensors | $290 | $1,110 |
$290
6,152
kWh
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $633 | $229 |
$401
8,476
kWh
|
$232
-
kW-mo/yr
|
|
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $496 | $1,810 |
$275
5,824
kWh
|
$221
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $12,739 | $77,094 |
$7,959
168,586
kWh
|
$4,780
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $10,329 | $69,238 |
$6,417
135,928
kWh
|
$3,912
-
kW-mo/yr
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs