| Assessment Year | 2011 |
|---|---|
| Principal Product | Transport Temperature Control Systems |
| NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
| SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
| Sales Range | $100 M to 500M |
| # of Employees | 270 |
| Plant Area |
234,000
ft2
|
| Annual Production | 40,000
pieces
|
| Production Hrs. Annual | 4,250
hrs
|
| Location (State) | Nebraska |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $169,247 | 4,177,200 |
kWh
|
$0.041 |
| Electricity Demand | $86,162 | 12,300 |
kW-mo/yr
|
$7.01 |
| Natural Gas | $126,397 | 23,102 |
MMBtu
|
$5.47 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $8,988 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,353 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $695 | $1,100 | - | - |
$695
-
MMBtu
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,500 | $105 |
$2,831
69,907
kWh
|
$669
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,238 | $4,669 |
$1,810
44,676
kWh
|
$428
-
kW-mo/yr
|
- | |
| 04 | 2.7135: Install occupancy sensors | $1,472 | $426 |
$1,472
36,329
kWh
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $615 | $1,273 |
$497
12,264
kWh
|
$118
-
kW-mo/yr
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $468 | $954 |
$350
8,656
kWh
|
$118
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $8,988 | $8,527 |
$6,960
171,832
kWh
|
$1,333
-
kW-mo/yr
|
$695
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $6,353 | $6,047 |
$5,138
126,847
kWh
|
$1,215
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs