| Assessment Year | 2008 |
|---|---|
| Principal Product | Mufflers |
| NAICS | 333413: Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
| SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 140 |
| Plant Area |
227,560
ft2
|
| Annual Production | 2,500,000
pieces
|
| Production Hrs. Annual | 3,406
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $227,313 | 6,035,334 |
kWh
|
$0.038 |
| Electricity Demand | $136,661 | 15,756 |
kW-mo/yr
|
$8.67 |
| Electricity Fees | $29,726 | - |
|
- |
| Natural Gas | $262,466 | 27,807 |
MMBtu
|
$9.44 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $46,129 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,849 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $4,302 | $1,140 | - | - | - |
$4,302
-
MMBtu
|
|
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $678 | $25 |
$375
10,218
kWh
|
$303
-
kW-mo/yr
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,055 | $500 |
$2,798
76,226
kWh
|
$2,257
-
kW-mo/yr
|
- | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $1,431 | $174 |
$793
21,507
kWh
|
$638
-
kW-mo/yr
|
- | - | |
| 05 | 2.7135: Install occupancy sensors | $758 | $1,001 |
$758
20,651
kWh
|
- | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,515 | $7,460 |
$2,499
68,087
kWh
|
$2,016
-
kW-mo/yr
|
- | - | |
| 07 | 2.6212: Turn off equipment during breaks, reduce operating time | $5,450 | $1,200 |
$5,450
148,500
kWh
|
- | - | - | |
| 08 | 2.3212: Optimize plant power factor | $19,032 | $19,062 | - | - | $19,032 | - | |
| 09 | 2.2437: Recover waste heat from equipment | $2,583 | $3,300 | - | - | - |
$2,583
-
MMBtu
|
|
| 10 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,325 | $800 |
$1,287
35,049
kWh
|
$1,038
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $46,129 | $34,662 |
$13,960
380,238
kWh
|
$6,252
-
kW-mo/yr
|
$19,032 |
$6,885
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $16,849 | $6,826 |
$10,668
290,644
kWh
|
$3,598
-
kW-mo/yr
|
- |
$2,583
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs