Assessment Year | 2006 |
---|---|
Principal Product | Rolls of plastic |
NAICS | 326112: Plastics Packaging Film and Sheet (including Laminated) Manufacturing |
SIC | 2671: Packaging Paper and Plastics Film, Coated and Laminated |
Sales Range | $50 M to 100M |
# of Employees | 100 |
Plant Area |
135,000
ft2
|
Annual Production | 107,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Minnesota |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $949,896 | 25,162,884 |
kWh
|
$0.038 |
Electricity Demand | $334,283 | 44,436 |
kW-mo/yr
|
$7.52 |
Natural Gas | $242,547 | 26,967 |
MMBtu
|
$8.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $49,450 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $39,778 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,847 | $47 |
$1,447
38,263
kWh
|
$400
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,645 | $2,882 |
$2,856
75,570
kWh
|
$789
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,417 | $3,991 |
$1,895
50,145
kWh
|
$522
-
kW-mo/yr
|
- | |
04 | 2.4133: Use most efficient type of electric motors | $2,519 | $194 |
$1,979
52,354
kWh
|
$540
-
kW-mo/yr
|
- | |
05 | 2.6218: Turn off equipment when not in use | $16,486 | $2,500 |
$10,623
281,037
kWh
|
$5,863
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,783 | $1,475 |
$2,972
78,624
kWh
|
$811
-
kW-mo/yr
|
- | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,437 | $1,550 |
$6,671
171,051
kWh
|
$1,766
-
kW-mo/yr
|
- | |
08 | 2.2511: Insulate bare equipment | $1,801 | $444 | - | - |
$1,801
-
MMBtu
|
|
09 | 2.2437: Recover waste heat from equipment | $7,280 | $25,700 | - | - |
$7,280
-
MMBtu
|
|
10 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,235 | $18 |
$27,190
719,196
kWh
|
- |
$(-25,955.0)
-
MMBtu
|
|
TOTAL RECOMMENDED | $49,450 | $38,801 |
$55,633
1,466,240
kWh
|
$10,691
-
kW-mo/yr
|
$(-16,874.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $39,778 | $37,233 |
$21,772
575,993
kWh
|
$8,925
-
kW-mo/yr
|
$9,081
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs