ITAC Assessment: IA0394
ITAC logo
ITAC Assessment: IA0394
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Ammunition
NAICS 332992: Small Arms Ammunition Manufacturing
SIC 3482: Small Arms Ammunition
Sales Range $100
M
to 500
M
# of Employees 1,100
Plant Area 960,000
ft2
Annual Production 52,900,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Minnesota

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $965,627 25,047,000
kWh
Electricity Demand $391,859 51,840
kW-mo/yr
Natural Gas $1,375,982 162,418
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $145,207 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $77,436

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $41,729 $4,200 $32,813
863,510
kWh
$8,916
-
kW-mo/yr
-
02 2.4234: Cool compressor air intake with heat exchanger $24,709 $6,500 $19,788
520,684
kWh
$4,921
-
kW-mo/yr
-
03 2.4231: Reduce the pressure of compressed air to the minimum required $10,998 $25 $8,626
227,005
kWh
$2,372
-
kW-mo/yr
-
04 2.4239: Eliminate or reduce compressed air usage $6,184 $74 $4,864
127,896
kWh
$1,320
-
kW-mo/yr
-
05 2.4239: Eliminate or reduce compressed air usage $17,292 $44,400 $11,203
294,840
kWh
$6,089
-
kW-mo/yr
-
06 2.2437: Recover waste heat from equipment $16,584 $15,900 $(-1,335.0)
(-35,119)
kWh
$(-363.0)
-
kW-mo/yr
$18,282
-
MMBtu
07 2.2437: Recover waste heat from equipment $25,628 $15,200 $(-445.0)
(-11,706)
kWh
$(-121.0)
-
kW-mo/yr
$26,194
-
MMBtu
08 2.2511: Insulate bare equipment $2,083 $1,969 - - $2,083
-
MMBtu
TOTAL RECOMMENDED $145,207 $88,268 $75,514
1,987,110
kWh
$23,134
-
kW-mo/yr
$46,559
-
MMBtu
TOTAL IMPLEMENTED $77,436 $10,725 $61,227
1,611,199
kWh
$16,209
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs