Assessment Year | 2006 |
---|---|
Principal Product | Electric Utility Equipment |
NAICS | 333923: Overhead Traveling Crane, Hoist, and Monorail System Manufacturing |
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $50 M to 100M |
# of Employees | 250 |
Plant Area |
135,000
ft2
|
Annual Production | 2,254
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $213,318 | 6,799,448 |
kWh
|
$0.031 |
Electricity Demand | $75,536 | 18,552 |
kW-mo/yr
|
$4.07 |
Natural Gas | $88,807 | 11,034 |
MMBtu
|
$8.05 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $66,792 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $65,513 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,190 | $4,918 |
$3,472
110,601
kWh
|
$718
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,183 | $6,385 |
$1,639
52,198
kWh
|
$544
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $2,587 | $3,234 |
$2,587
82,391
kWh
|
- | - | |
04 | 2.7124: Make a practice of turning off lights when not needed | $2,069 | $1,000 |
$2,069
65,894
kWh
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,869 | $480 |
$3,205
102,063
kWh
|
$664
-
kW-mo/yr
|
- | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,922 | $52 |
$2,422
77,126
kWh
|
$500
-
kW-mo/yr
|
- | |
07 | 2.4133: Use most efficient type of electric motors | $1,279 | $1,972 |
$1,092
28,798
kWh
|
$187
-
kW-mo/yr
|
- | |
08 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $47,693 | $45,600 |
$(-1,878.0)
(-57,754)
kWh
|
$(-388.0)
-
kW-mo/yr
|
$49,959
-
MMBtu
|
|
TOTAL RECOMMENDED | $66,792 | $63,641 |
$14,608
461,317
kWh
|
$2,225
-
kW-mo/yr
|
$49,959
-
MMBtu
|
||
TOTAL IMPLEMENTED | $65,513 | $61,669 |
$13,516
432,519
kWh
|
$2,038
-
kW-mo/yr
|
$49,959
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs