ITAC Assessment: IA0379
ITAC logo
ITAC Assessment: IA0379
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Medical Instruments
NAICS 339112: Surgical and Medical Instrument Manufacturing
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 48,200
ft2
Annual Production 3,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $112,227 1,308,240
kWh
Electricity Fees $1,713 -
Natural Gas $8,985 945
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,362 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4221: Install compressor air intakes in coolest locations $222 $182 $222
2,630
kWh
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $109 $50 $109
2,238
kWh
03 2.7224: Reduce space conditioning during non-working hours $602 $800 $602
7,115
kWh
04 2.7314: Reduce ventilation air $2,513 $320 $2,513
29,702
kWh
05 2.7135: Install occupancy sensors $916 $1,155 $916
10,830
kWh
TOTAL RECOMMENDED $4,362 $2,507 $4,362
52,515
kWh
TOTAL IMPLEMENTED - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs