ITAC Assessment: IA0378
ITAC logo
ITAC Assessment: IA0378
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Diversified Steel Fabrication
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 195,000
ft2
Annual Production 1,000
ton
Production Hrs. Annual 2,142
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $76,136 1,181,529
kWh
Electricity Demand $11,400 1,195
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,000 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $576

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $576 $385 $576
8,033
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,533 $1,936 $1,397
20,864
kWh
$136
-
kW-mo/yr
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,476 $2,255 $1,397
8,967
kWh
$79
-
kW-mo/yr
04 2.7135: Install occupancy sensors $415 $1,155 $415
5,759
kWh
-
TOTAL RECOMMENDED $4,000 $5,731 $3,785
43,623
kWh
$215
-
kW-mo/yr
TOTAL IMPLEMENTED $576 $385 $576
8,033
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs