Assessment Year | 2005 |
---|---|
Principal Product | Half Shell Bearings and Solid Flanged Bearings |
NAICS | 333613: Mechanical Power Transmission Equipment Manufacturing |
SIC | 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 450 |
Plant Area |
176,000
ft2
|
Annual Production | 15,000,000
lb
|
Production Hrs. Annual | 4,500
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $355,114 | 13,636,430 |
kWh
|
$0.026 |
Electricity Demand | $96,117 | 34,620 |
kW-mo/yr
|
$2.78 |
Electricity Fees | $1,188 | - |
|
- |
Natural Gas | $138,235 | 17,840 |
MMBtu
|
$7.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,738 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,120 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,120 | $1,065 |
$878
33,885
kWh
|
$242
-
kW-mo/yr
|
|
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $23,794 | $53,000 |
$18,648
720,000
kWh
|
$5,146
-
kW-mo/yr
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,778 | $3,095 |
$1,474
56,899
kWh
|
$304
-
kW-mo/yr
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,898 | $31,761 |
$6,185
238,792
kWh
|
$1,713
-
kW-mo/yr
|
|
05 | 2.7135: Install occupancy sensors | $1,048 | $1,694 |
$1,048
40,481
kWh
|
- | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,100 | $6,924 |
$3,997
154,350
kWh
|
$1,103
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $40,738 | $97,539 |
$32,230
1,244,407
kWh
|
$8,508
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $1,120 | $1,065 |
$878
33,885
kWh
|
$242
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs