ITAC Assessment: IA0343
ITAC logo
ITAC Assessment: IA0343
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product electric fork trucks
NAICS 333924: Industrial Truck, Tractor, Trailer, and Stacker Machinery Manufacturing
SIC 3537: Industrial Trucks, Tractors, Trailers, and Stackers
Sales Range $50
M
to 100
M
# of Employees 210
Plant Area 180,000
ft2
Annual Production 8,000
pieces
Production Hrs. Annual 4,836
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $157,078 3,935,600
kWh
Electricity Demand $56,996 10,852
kW-mo/yr
Natural Gas $234,586 28,795
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $56,673 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $45,877

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,846 $446 $1,871
60,455
kWh
$1,263
-
kW-mo/yr
- $(-288.0)
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,120 $1,866 $550
17,711
kWh
$570
-
kW-mo/yr
- -
03 2.4133: Use most efficient type of electric motors $125 $70 $62
1,992
kWh
$63
-
kW-mo/yr
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,173 $7,306 $561
18,096
kWh
$885
-
kW-mo/yr
$1,727
-
MMBtu
-
05 2.2614: Use cooling tower or economizer to replace chiller cooling $817 $1,230 $817
26,353
kWh
- - -
06 2.2437: Recover waste heat from equipment $8,859 $9,696 $(-155.0)
(-4,992)
kWh
$(-163.0)
-
kW-mo/yr
$9,177
-
MMBtu
-
07 4.111: Add equipment/ operators to reduce production bottleneck $39,733 $10,000 $1,209
39,000
kWh
$(-244.0)
-
kW-mo/yr
$7,568
-
MMBtu
$31,200
TOTAL RECOMMENDED $56,673 $30,614 $4,915
158,615
kWh
$2,374
-
kW-mo/yr
$18,472
-
MMBtu
$30,912
TOTAL IMPLEMENTED $45,877 $17,822 $3,703
119,543
kWh
$1,967
-
kW-mo/yr
$9,295
-
MMBtu
$30,912
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs