Assessment Year | 2001 |
---|---|
Principal Product | plastic bottles and caps |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 105 |
Plant Area |
111,000
ft2
|
Annual Production | 9,000,000
lb
|
Production Hrs. Annual | 8,520
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $220,027 | 9,146,000 |
kWh
|
$0.024 |
Electricity Demand | $123,404 | 17,424 |
kW-mo/yr
|
$7.08 |
Natural Gas | $9,102 | 1,393 |
MMBtu
|
$6.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $688,339 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,621 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,910 | $120 |
$3,459
145,350
kWh
|
$1,451
-
kW-mo/yr
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $4,711 | $2,000 |
$3,317
139,371
kWh
|
$1,394
-
kW-mo/yr
|
- | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $4,261 | $65 |
$3,001
126,096
kWh
|
$1,260
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,199 | - |
$2,961
124,392
kWh
|
$1,238
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,590 | $4,978 |
$833
34,980
kWh
|
$757
-
kW-mo/yr
|
- | |
06 | 2.7135: Install occupancy sensors | $571 | $1,397 |
$571
23,945
kWh
|
- | - | |
07 | 4.441: Install automatic packing equipment | $511,200 | $300,000 | - | - | $511,200 | |
08 | 4.441: Install automatic packing equipment | $127,800 | $107,000 | - | - | $127,800 | |
09 | 4.441: Install automatic packing equipment | $18,225 | $42,125 | - | - | $18,225 | |
10 | 4.441: Install automatic packing equipment | $10,872 | $7,000 | - | - | $10,872 | |
TOTAL RECOMMENDED | $688,339 | $464,685 |
$14,142
594,134
kWh
|
$6,100
-
kW-mo/yr
|
$668,097 | ||
TOTAL IMPLEMENTED | $9,621 | $2,120 |
$6,776
284,721
kWh
|
$2,845
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs