Assessment Year | 2001 |
---|---|
Principal Product | vinyl windows |
NAICS |
n/a
|
SIC | 2431: Millwork |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
175,000
ft2
|
Annual Production | 450,000
pieces
|
Production Hrs. Annual | 5,120
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $52,548 | 2,264,094 |
kWh
|
$0.023 |
Electricity Demand | $35,169 | 5,940 |
kW-mo/yr
|
$5.92 |
Natural Gas | $27,822 | 4,728 |
MMBtu
|
$5.88 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $135,527 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,188 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,585 | $989 |
$4,150
179,634
kWh
|
$2,435
-
kW-mo/yr
|
- | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $512 | $116 |
$348
15,051
kWh
|
$164
-
kW-mo/yr
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,284 | $887 |
$1,439
62,280
kWh
|
$845
-
kW-mo/yr
|
- | - | - | |
04 | 3.5215: Avoid contamination of end pieces and reuse as feed stock | $18,000 | $22,100 | - | - |
$18,000
-
lb
|
- | - | |
05 | 4.423: Move product using mechanical means | $96,543 | $50,000 | - | - | - | $94,043 | $2,500 | |
06 | 4.322: Eliminate old stock and modify inventory control | $11,603 | $1,088 | - | - | - | $11,603 | - | |
TOTAL RECOMMENDED | $135,527 | $75,180 |
$5,937
256,965
kWh
|
$3,444
-
kW-mo/yr
|
$18,000
-
lb
|
$105,646 | $2,500 | ||
TOTAL IMPLEMENTED | $36,188 | $24,177 |
$4,150
179,634
kWh
|
$2,435
-
kW-mo/yr
|
$18,000
-
lb
|
$11,603 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs