Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product fluid milk
NAICS
n/a
SIC 2022: Natural, Processed, and Imitation Cheese
Sales Range $10
M
to 50
M
# of Employees 44
Plant Area 12,000
ft2
Annual Production 6,000
ton
Production Hrs. Annual 4,680
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $163,999 4,803,634
kWh
Electricity Demand $91,391 11,412
kW-mo/yr
Natural Gas $63,924 20,231
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,870 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,500

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.2111: Install steam trap $1,500 $628 - - $1,500
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,337 $6,470 $810
23,740
kWh
$527
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,072 $363 $670
19,637
kWh
$402
-
kW-mo/yr
- -
04 2.2511: Insulate bare equipment $485 $195 $303
8,792
kWh
$182
-
kW-mo/yr
- -
05 4.221: Use only amount of packaging material necessary $8,476 $21,000 - - - $8,476
TOTAL RECOMMENDED $12,870 $28,656 $1,783
52,169
kWh
$1,111
-
kW-mo/yr
$1,500
-
MMBtu
$8,476
TOTAL IMPLEMENTED $1,500 $628 - - $1,500
-
MMBtu
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs