Assessment Year | 1999 |
---|---|
Principal Product | Aerial Boom Lifts |
NAICS |
n/a
|
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 275 |
Plant Area |
221,000
ft2
|
Annual Production | 960
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $87,278 | 3,387,456 |
kWh
|
$0.026 |
Electricity Demand | $27,130 | 9,036 |
kW-mo/yr
|
$3.00 |
Natural Gas | $78,154 | 16,404 |
MMBtu
|
$4.76 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $569,360 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,046 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Gaseous Waste Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,090 | $294 |
$877
34,877
kWh
|
$213
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $360 | $30 |
$299
11,723
kWh
|
$61
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,122 | - |
$5,079
201,641
kWh
|
$1,043
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $399 | $1,324 |
$331
13,189
kWh
|
$68
-
kW-mo/yr
|
- | - | - | - | |
05 | 4.111: Add equipment/ operators to reduce production bottleneck | $540,000 | $1,501,800 | - | - | - | - | - | $540,000 | |
06 | 3.3113: Use other methods for neutralization | $12,382 | $7,990 |
$(-56.0)
(-2,345)
kWh
|
$(-161.0)
-
kW-mo/yr
|
$12,599
-
gal
|
- | - | - | |
07 | 3.3128: Utilize other methods to remove contaminants | $4,907 | $200 | - | - | - |
$4,907
-
lb
|
- | - | |
08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $3,144 | $7,480 | - | - | - |
$3,144
-
lb
|
- | - | |
09 | 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings | $956 | $143 | - | - | - | - |
$956
-
lb
|
- | |
TOTAL RECOMMENDED | $569,360 | $1,519,261 |
$6,530
259,085
kWh
|
$1,224
-
kW-mo/yr
|
$12,599
-
gal
|
$8,051
-
lb
|
$956
-
lb
|
$540,000 | ||
TOTAL IMPLEMENTED | $2,046 | $437 |
$877
34,877
kWh
|
$213
-
kW-mo/yr
|
- | - |
$956
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Gaseous Waste Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs