Assessment Year | 1999 |
---|---|
Principal Product | corrugated cardboard |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
150,000
ft2
|
Annual Production | 55,000
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $147,624 | 4,647,128 |
kWh
|
$0.032 |
Electricity Demand | $35,919 | 10,500 |
kW-mo/yr
|
$3.42 |
Natural Gas | $165,447 | 58,639 |
MMBtu
|
$2.82 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $53,624 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,449 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,169 | $382 |
$3,973
181,419
kWh
|
$2,196
-
kW-mo/yr
|
- | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,587 | $2,500 | - | - |
$3,587
-
MMBtu
|
- | |
03 | 2.2511: Insulate bare equipment | $2,904 | $3,300 | - | - |
$2,904
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,498 | $11,043 |
$1,487
67,995
kWh
|
$1,011
-
kW-mo/yr
|
- | - | |
05 | 2.4133: Use most efficient type of electric motors | $319 | $640 |
$206
9,379
kWh
|
$113
-
kW-mo/yr
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,637 | $2,184 |
$1,056
48,359
kWh
|
$581
-
kW-mo/yr
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $952 | $50 |
$544
24,912
kWh
|
$408
-
kW-mo/yr
|
- | - | |
08 | 2.7135: Install occupancy sensors | $294 | $1,264 |
$294
13,482
kWh
|
- | - | - | |
09 | 2.6218: Turn off equipment when not in use | $264 | $102 |
$264
12,016
kWh
|
- | - | - | |
10 | 4.425: Eliminate/reduce redundant inspections | $35,000 | $7,000 | - | - | - | $35,000 | |
TOTAL RECOMMENDED | $53,624 | $28,465 |
$7,824
357,562
kWh
|
$4,309
-
kW-mo/yr
|
$6,491
-
MMBtu
|
$35,000 | ||
TOTAL IMPLEMENTED | $14,449 | $17,475 |
$7,074
323,271
kWh
|
$3,788
-
kW-mo/yr
|
$3,587
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs