| Assessment Year | 1998 |
|---|---|
| Principal Product | organic herb and spice products |
| NAICS |
n/a
|
| SIC | 2099: Food Preparations, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 250 |
| Plant Area |
80,000
ft2
|
| Annual Production | 5,000,000
lb
|
| Production Hrs. Annual | 4,290
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $46,731 | 1,498,828 |
kWh
|
$0.031 |
| Electricity Demand | $34,106 | 4,536 |
kW-mo/yr
|
$7.52 |
| Natural Gas | $10,040 | 2,002 |
MMBtu
|
$5.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $291,552 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $291,552 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,330 | $21,549 |
$2,933
94,373
kWh
|
$2,397
-
kW-mo/yr
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $279 | $372 |
$160
5,275
kWh
|
$119
-
kW-mo/yr
|
- | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $37 | $108 |
$19
586
kWh
|
$18
-
kW-mo/yr
|
- | - | |
| 04 | 4.425: Eliminate/reduce redundant inspections | $199,680 | $35,485 | - | - | $199,680 | - | |
| 05 | 4.111: Add equipment/ operators to reduce production bottleneck | $59,520 | $111,000 | - | - | $49,920 | $9,600 | |
| 06 | 3.1161: Eliminate/reduce an operation | $24,960 | $20,000 | - | - | $24,960 | - | |
| 07 | 4.652: Replace existing equipment with more suitable substitutes | $1,746 | $75 | - | - | - | $1,746 | |
| TOTAL RECOMMENDED | $291,552 | $188,589 |
$3,112
100,234
kWh
|
$2,534
-
kW-mo/yr
|
$274,560 | $11,346 | ||
| TOTAL IMPLEMENTED | $291,552 | $188,589 |
$3,112
100,234
kWh
|
$2,534
-
kW-mo/yr
|
$274,560 | $11,346 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs