Assessment Year | 1987 |
---|---|
Principal Product | BEDRM & DIN RM FURNITURE |
NAICS |
n/a
|
SIC | 2511: Wood Household Furniture, Except Upholstered |
Sales Range | $10 M to 50M |
# of Employees | 184 |
Plant Area |
n/a
|
Annual Production | 12,500
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $208,865 | 3,580,891 |
kWh
|
$0.058 |
Natural Gas | $21,699 | 3,562 |
MMBtu
|
$6.09 |
Coal | $33,451 | 26,493 |
MMBtu
|
$1.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,413 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,723 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Coal Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,616 | $2,484 |
$4,616
79,132
kWh
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $1,287 | $2,086 |
$1,287
21,981
kWh
|
- | |
03 | 2.4312: Improve lubrication practices | $1,463 | - |
$1,463
25,205
kWh
|
- | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,625 | - |
$1,625
27,843
kWh
|
- | |
05 | 2.2121: Increase amount of condensate returned | $4,440 | $400 | - |
$4,440
-
MMBtu
|
|
06 | 2.2136: Install / repair insulation on steam lines | $980 | $2,337 | - |
$980
-
MMBtu
|
|
07 | 2.2437: Recover waste heat from equipment | $11,690 | $2,000 | - |
$11,690
-
MMBtu
|
|
08 | 2.4221: Install compressor air intakes in coolest locations | $312 | $150 |
$312
5,275
kWh
|
- | |
TOTAL RECOMMENDED | $26,413 | $9,457 |
$9,303
159,436
kWh
|
$17,110
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,723 | $7,457 |
$9,303
159,436
kWh
|
$5,420
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Coal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs