ITAC Assessment: IA0202
ITAC logo
ITAC Assessment: IA0202
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product frozen meat products
NAICS
n/a
SIC 2038: Frozen Specialties, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 250
Plant Area 78,000
ft2
Annual Production 390,000,000
lb
Production Hrs. Annual 5,616
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $196,207 9,726,260
kWh
Electricity Demand $205,401 26,400
kW-mo/yr
Natural Gas $284,446 72,458
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,462,210 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $74,907

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $772 $1,000 $436
21,688
kWh
$336
-
kW-mo/yr
- - - - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,103 $4,026 $421
20,809
kWh
$682
-
kW-mo/yr
- - - - - - -
03 2.4234: Cool compressor air intake with heat exchanger $1,000 $500 $655
32,532
kWh
$345
-
kW-mo/yr
- - - - - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $558 $25 $306
15,240
kWh
$252
-
kW-mo/yr
- - - - - - -
05 2.1233: Analyze flue gas for proper air/fuel ratio $421 $500 - - $511
-
MMBtu
- - $(-90.0) - - -
06 2.1213: Direct warmest air to combustion intake $410 $566 - - $410
-
MMBtu
- - - - - -
07 3.4151: Minimize water usage $19,371 $25,051 - - $7,024
-
MMBtu
$12,347
-
Tgal
- - - - -
08 3.5315: Lease / purchase baler; sell cardboard to recycler $10,280 $7,990 - - - - $24,960
-
lb
$(-4,680.0) - - $(-10,000.0)
09 4.441: Install automatic packing equipment $1,151,761 $500,000 $(-1,397.0)
(-69,168)
kWh
$(-1,242.0)
-
kW-mo/yr
- - - $1,404,000 - $(-249,600.0) -
10 4.441: Install automatic packing equipment $215,761 $500,000 $(-1,397.0)
(-69,168)
kWh
$(-1,242.0)
-
kW-mo/yr
- - - $468,000 - $(-249,600.0) -
11 4.441: Install automatic packing equipment $31,068 $7,800 $(-41.0)
(-2,052)
kWh
$(-91.0)
-
kW-mo/yr
- - - $31,200 - - -
12 2.8113: Purchase gas directly from a contract gas supplier $28,526 $2,950 - - - - - - $28,526 - -
13 4.211: Consider use / purchase of bulk materials where possible $1,179 $3,763 - - - - - - $1,179 - -
TOTAL RECOMMENDED $1,462,210 $1,054,171 $(-1,017.0)
(-50,119)
kWh
$(-960.0)
-
kW-mo/yr
$7,945
-
MMBtu
$12,347
-
Tgal
$24,960
-
lb
$1,898,430 $29,705 $(-499,200.0) $(-10,000.0)
TOTAL IMPLEMENTED $74,907 $28,554 $1,777
88,217
kWh
$1,524
-
kW-mo/yr
$511
-
MMBtu
- $24,960
-
lb
$26,430 $29,705 - $(-10,000.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs