Assessment Year | 1998 |
---|---|
Principal Product | frozen meat products |
NAICS |
n/a
|
SIC | 2038: Frozen Specialties, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 250 |
Plant Area |
78,000
ft2
|
Annual Production | 390,000,000
lb
|
Production Hrs. Annual | 5,616
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $196,207 | 9,726,260 |
kWh
|
$0.020 |
Electricity Demand | $205,401 | 26,400 |
kW-mo/yr
|
$7.78 |
Natural Gas | $284,446 | 72,458 |
MMBtu
|
$3.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,462,210 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $74,907 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $772 | $1,000 |
$436
21,688
kWh
|
$336
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,103 | $4,026 |
$421
20,809
kWh
|
$682
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.4234: Cool compressor air intake with heat exchanger | $1,000 | $500 |
$655
32,532
kWh
|
$345
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $558 | $25 |
$306
15,240
kWh
|
$252
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $421 | $500 | - | - |
$511
-
MMBtu
|
- | - | $(-90.0) | - | - | - | |
06 | 2.1213: Direct warmest air to combustion intake | $410 | $566 | - | - |
$410
-
MMBtu
|
- | - | - | - | - | - | |
07 | 3.4151: Minimize water usage | $19,371 | $25,051 | - | - |
$7,024
-
MMBtu
|
$12,347
-
Tgal
|
- | - | - | - | - | |
08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $10,280 | $7,990 | - | - | - | - |
$24,960
-
lb
|
$(-4,680.0) | - | - | $(-10,000.0) | |
09 | 4.441: Install automatic packing equipment | $1,151,761 | $500,000 |
$(-1,397.0)
(-69,168)
kWh
|
$(-1,242.0)
-
kW-mo/yr
|
- | - | - | $1,404,000 | - | $(-249,600.0) | - | |
10 | 4.441: Install automatic packing equipment | $215,761 | $500,000 |
$(-1,397.0)
(-69,168)
kWh
|
$(-1,242.0)
-
kW-mo/yr
|
- | - | - | $468,000 | - | $(-249,600.0) | - | |
11 | 4.441: Install automatic packing equipment | $31,068 | $7,800 |
$(-41.0)
(-2,052)
kWh
|
$(-91.0)
-
kW-mo/yr
|
- | - | - | $31,200 | - | - | - | |
12 | 2.8113: Purchase gas directly from a contract gas supplier | $28,526 | $2,950 | - | - | - | - | - | - | $28,526 | - | - | |
13 | 4.211: Consider use / purchase of bulk materials where possible | $1,179 | $3,763 | - | - | - | - | - | - | $1,179 | - | - | |
TOTAL RECOMMENDED | $1,462,210 | $1,054,171 |
$(-1,017.0)
(-50,119)
kWh
|
$(-960.0)
-
kW-mo/yr
|
$7,945
-
MMBtu
|
$12,347
-
Tgal
|
$24,960
-
lb
|
$1,898,430 | $29,705 | $(-499,200.0) | $(-10,000.0) | ||
TOTAL IMPLEMENTED | $74,907 | $28,554 |
$1,777
88,217
kWh
|
$1,524
-
kW-mo/yr
|
$511
-
MMBtu
|
- |
$24,960
-
lb
|
$26,430 | $29,705 | - | $(-10,000.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs