ITAC Assessment: IA0198
ITAC logo
ITAC Assessment: IA0198
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product bottled salad dressings
NAICS
n/a
SIC 2035: Pickled Fruits and Vegetables, Vegetable Sauces and Seasonings, and Salad Dressings
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 43,000
ft2
Annual Production 28,000,000
lb
Production Hrs. Annual 2,340
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $62,760 1,179,953
kWh
Natural Gas $33,562 8,513
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $431,377 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,625

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Personnel Changes Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,251 $340 $1,251
23,447
kWh
- -
02 2.4133: Use most efficient type of electric motors $1,022 $2,256 $1,022
19,343
kWh
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $524 $1,100 $524
9,965
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $179 $503 $179
3,517
kWh
- -
05 2.7135: Install occupancy sensors $173 $133 $173
3,224
kWh
- -
06 2.4231: Reduce the pressure of compressed air to the minimum required $140 $25 $140
2,638
kWh
- -
07 3.5317: Sell / offer by-product as animal feed $17,160 $250 - - $17,160
08 4.441: Install automatic packing equipment $186,435 $208,600 $(-765.0)
(-14,361)
kWh
$187,200 -
09 4.441: Install automatic packing equipment $154,293 $149,500 $(-1,707.0)
(-31,946)
kWh
$156,000 -
10 4.441: Install automatic packing equipment $70,200 $180,000 - $70,200 -
TOTAL RECOMMENDED $431,377 $542,707 $817
15,827
kWh
$413,400 $17,160
TOTAL IMPLEMENTED $2,625 $3,232 $2,625
49,531
kWh
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs