| Assessment Year | 1998 |
|---|---|
| Principal Product | tire and industrial chains |
| NAICS |
n/a
|
| SIC | 3496: Miscellaneous Fabricated Wire Products |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
325,000
ft2
|
| Annual Production | 19,000
ton
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $431,270 | 13,729,777 |
kWh
|
$0.031 |
| Electricity Demand | $209,493 | 27,912 |
kW-mo/yr
|
$7.51 |
| Natural Gas | $235,176 | 81,052 |
MMBtu
|
$2.90 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $109,362 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,304 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,107 | $21,359 |
$9,517
303,048
kWh
|
$3,590
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,917 | $3,000 | - | - |
$4,917
-
MMBtu
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,197 | $4,877 |
$1,123
35,756
kWh
|
$1,074
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.2511: Insulate bare equipment | $1,500 | $1,695 | - | - |
$1,500
-
MMBtu
|
- | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $877 | $15 |
$635
20,223
kWh
|
$242
-
kW-mo/yr
|
- | - | - | |
| 06 | 4.441: Install automatic packing equipment | $74,880 | $52,000 | - | - | - | $74,880 | - | |
| 07 | 2.3137: Use power during off-peak periods | $11,884 | - | - | - | - | $(-986.0) | $12,870 | |
| TOTAL RECOMMENDED | $109,362 | $82,946 |
$11,275
359,027
kWh
|
$4,906
-
kW-mo/yr
|
$6,417
-
MMBtu
|
$73,894 | $12,870 | ||
| TOTAL IMPLEMENTED | $15,304 | $26,236 |
$10,640
338,804
kWh
|
$4,664
-
kW-mo/yr
|
- | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs