ITAC Assessment: IA0183
ITAC logo
ITAC Assessment: IA0183
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product animal vaccines
NAICS
n/a
SIC 2834: Pharmaceutical Preparations
Sales Range $10
M
to 50
M
# of Employees 65
Plant Area 39,000
ft2
Annual Production 32,000,000
pieces
Production Hrs. Annual 2,340
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $156,262 3,362,837
kWh
Electricity Demand $19,420 7,824
kW-mo/yr
Natural Gas $56,781 13,920
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $50,150 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,304

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Water Consumption Savings By-product Production Savings
01 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $6,078 $68,000 $1,892
41,325
kWh
$158
-
kW-mo/yr
$4,028
-
MMBtu
- - - - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,353 $3,856 $1,050
22,860
kWh
$303
-
kW-mo/yr
- - - - - - - -
03 2.7135: Install occupancy sensors $1,081 $798 $1,081
23,740
kWh
- - - - - - - - -
04 3.4115: Recover and reuse cooling water $6,010 $5,809 $(-21.0)
(-586)
kWh
$(-4.0)
-
kW-mo/yr
- $2,854
-
Tgal
- - - - $3,181
-
Tgal
-
05 3.5315: Lease / purchase baler; sell cardboard to recycler $4,639 $8,400 - - - - $2,516
-
lb
$(-127.0) - - - $2,250
06 3.6192: Use a less expensive method of waste removal $2,112 $600 - - - - $2,112
-
lb
- - - - -
07 3.5311: Recover and reuse waste material $315 - - - - - - - - $315 - -
08 2.8113: Purchase gas directly from a contract gas supplier $17,122 $4,200 - - - - - - $17,122 - - -
09 4.441: Install automatic packing equipment $11,440 $50,000 - - - - - $11,440 - - - -
TOTAL RECOMMENDED $50,150 $141,663 $4,002
87,339
kWh
$457
-
kW-mo/yr
$4,028
-
MMBtu
$2,854
-
Tgal
$4,628
-
lb
$11,313 $17,122 $315 $3,181
-
Tgal
$2,250
TOTAL IMPLEMENTED $31,304 $85,056 $2,942
64,185
kWh
$461
-
kW-mo/yr
$4,028
-
MMBtu
- $4,628
-
lb
$(-127.0) $17,122 - - $2,250
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Water Consumption Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs